ESRS
ESRS E5 Resource use and circular economy: Disclosure Requirements, Datapoints and What Changes in the Simplified ESRS
ESRS E5 in the 2023 and 2026 versions: each disclosure requirement, the deleted E5-6 and what Delegated Regulation (EU) 2026/1563 changed for waste.
Summary
ESRS E5 Resource use and circular economy is the topical standard that sets the disclosure requirements for an undertaking whose resource inflows, resource outflows or waste give rise to material impacts, risks or opportunities.
It has six disclosure requirements in the 2023 version and five in the 2026 version, where E5-6 is deleted.
ESRS E5 exists in two versions: Annex I to Delegated Regulation (EU) 2023/2772 as amended by 2025/1416, and Annex I to Delegated Regulation (EU) 2026/1563. Both are delegated regulations and apply directly, without national transposition. E5 is one part of the sustainability disclosures under the Corporate Sustainability Reporting Directive (CSRD) explained.
The table compares the two versions as of 25 November 2026. The sections below follow its order and name the paragraph behind each line. Every code and paragraph number carries its version, because E5-4 and E5-5 exist in both versions with different paragraphs.
| Point | 2023 version | 2026 version |
|---|---|---|
| Instrument | Delegated Regulation (EU) 2023/2772 as amended by 2025/1416; see the three ESRS delegated acts | Delegated Regulation (EU) 2026/1563, replacing Annex I of 2023/2772 |
| Financial years | FY 2024 and FY 2025; FY 2026 as one option | Financial years beginning on or after 1 January 2027; FY 2026 as one option |
| Disclosure requirements | E5-1 to E5-6, plus paragraph 11 related to ESRS 2 IRO-1 | E5-1 to E5-5 |
| Policies, actions, targets | MDR-P, MDR-A, MDR-T | GDR-P, GDR-A, GDR-T |
| Anticipated financial effects | E5-6 | ESRS 2 paragraph 27 |
| Sub-topics | ESRS 1 AR 16 | ESRS E5 paragraph 6 |
| Applied with | ESRS 1 general requirements of the same act | ESRS 1 General requirements of the same act |
What ESRS E5 Covers
ESRS E5 covers how an undertaking uses resources and how it manages what leaves its operations as products and waste, and it applies when the topic relates to a material impact, risk or opportunity. The 2026 version adds that its disclosure requirements complement ESRS 2 SBM-3 and IRO-2 (ESRS E5 paragraph 3).
Three Sub-Topics and the Standards Around Them
The 2026 version sets disclosure requirements for three sub-topics: resource inflows, resource outflows related to products and services, and resource outflows related to waste (ESRS E5 paragraph 6). The 2023 version listed the same three in ESRS 1 AR 16. They belong to the topical ESRS under the European Sustainability Reporting Standards.
E5 sits next to other topical standards. The 2026 version names E1, E2, E3, E4, S3 and S4 in paragraph 7(a) to (f), and the 2023 version names E1 to E4 and S3 in paragraphs 6 to 8. The border list below gives one line for each.
Two Versions and the Financial Years They Apply To
Financial years 2024 and 2025 use the 2023 version, FY 2026 may use either version, and financial years beginning on or after 1 January 2027 use the 2026 version (Articles 2 and 3 of Delegated Regulation (EU) 2026/1563).
Delegated Regulation (EU) 2023/2772 applies from 1 January 2024, and 2025/1416 applies to financial years beginning on or after 1 January 2025.
The 2026 act of 3 July 2026 has been in force since 10 November 2026, as of 25 November 2026. It replaces Annex I of 2023/2772 and does not repeal that regulation.
For FY 2026 the undertaking chooses under Article 2 of Delegated Regulation (EU) 2026/1563: the 2023 set as last amended by 2025/1416, the new Annex I, or the 2025/1416 text with reliefs from ESRS 1 paragraphs 27, 32 to 33, 74 to 75, 90, 91, 92, 106 and 110. The statement says which version applies.
EFRAG's technical advice on the simplified ESRS is not the revised ESRS, and its paragraph numbers are not law. For the mechanics of the FY 2026 option, see the choice between the versions under the revised (simplified) ESRS.
When ESRS E5 Must Be Reported
The two versions differ on when E5 must be reported: the 2023 version always requires one paragraph of E5, while the 2026 version asks for E5 information only where the topic relates to material impacts, risks and opportunities.
The rules sit in ESRS 1 paragraphs 29 to 32 (2023) and ESRS E5 paragraphs 1 to 3 (2026).
The 2023 Text: One Paragraph Reported in Every Case
Under the 2023 version, the undertaking shall always disclose, irrespective of the outcome of its materiality assessment, the topical disclosure requirements related to IRO-1 that ESRS 2 Appendix C lists, which for E5 is paragraph 11 (ESRS 1 paragraph 29 of Delegated Regulation (EU) 2023/2772).
Paragraph 11 asks for the screening of assets and activities, with the methodologies, assumptions and tools used, and for consultations, in particular with affected communities (points (a) and (b)). For a topic other than climate change that is found not material, the undertaking may briefly explain its conclusions (ESRS 1 paragraph 32).
The 2026 Text: Reported if the Topic Is Material
The 2026 version requires E5 information if the topic relates to material impacts, risks and opportunities, and if not all sub-topics are material, paragraph 30 of ESRS 1 applies (ESRS E5 paragraphs 1 and 2). Whether the topic is material comes from the materiality assessment under the ESRS.
The 2026 E5 has no paragraph related to IRO-1. The link to the assessment runs through ESRS 2 SBM-3 and IRO-2 (ESRS E5 paragraph 3), and the phase-in lists in paragraphs 125 and 127 of ESRS 1 name no E5 disclosure requirement.
The Disclosure Requirements in Both Versions
ESRS E5 has six disclosure requirements in the 2023 version, E5-1 to E5-6, and five in the 2026 version, E5-1 to E5-5, because the 2026 version deletes E5-6. The table maps each code to its paragraphs in both versions, and E5-4 and E5-5 carry the data.
| Area | 2023 version: code and title (paragraphs) | 2026 version: code and title (paragraphs) | Change |
|---|---|---|---|
| Process | Related to ESRS 2 IRO-1 (11) | None in E5 | Paragraph 11 is gone |
| Policies | E5-1 Policies related to resource use and circular economy (12 to 16) | E5-1 Policies related to resource use and circular economy (8, 9) | MDR-P becomes GDR-P; circular economy and eco-design explanation added |
| Actions | E5-2 Actions and resources related to resource use and circular economy (17 to 20) | E5-2 Actions and resources related to resource use and circular economy (10) | MDR-A becomes GDR-A |
| Targets | E5-3 Targets related to resource use and circular economy (21 to 27) | E5-3 Targets related to resource use and circular economy (11) | MDR-T becomes GDR-T |
| Inflows | E5-4 Resource inflows (28 to 32) | E5-4 Resource inflows (12, 13) | Key materials replace total weights |
| Outflows | E5-5 Resource outflows (33 to 40) | E5-5 Resource outflows (14 to 17) | Designed recyclability and unknown destination added |
| Financial effects | E5-6 Anticipated financial effects from resource use and circular economy-related impacts, risks and opportunities (41 to 43) | Deleted | Effects through ESRS 2 paragraph 27 |
E5-1 to E5-3 point to the policy, action and target requirements of ESRS 2. The inflow, product and waste items below carry the data.
Policies, Actions and Targets: E5-1 to E5-3
In the 2026 version E5-1, E5-2 and E5-3 (paragraphs 8 to 11) each refer to ESRS 2 GDR-P, GDR-A and GDR-T, and only E5-1 adds an item of its own: if the undertaking integrates circular economy principles or eco-design requirements in key products and services, it explains how (paragraph 9).
The 2023 E5-1 (paragraphs 12 to 16) used MDR-P and listed two matters, virgin resources and renewable sourcing (paragraph 15(a), (b)). E5-2 (paragraphs 17 to 20) let the undertaking specify matters (a) to (f).
E5-3 (paragraphs 21 to 27) added matters (a) to (f), a waste hierarchy layer (paragraph 25) and a mandatory or voluntary statement (paragraph 27).
ESRS 2 renamed MDR-P, MDR-A and MDR-T as GDR-P, GDR-A and GDR-T in the 2026 version. The content of both sets is in the minimum and general disclosure requirements for policies, actions and targets.
Resource Inflows: E5-4
The 2026 E5-4 asks for the key materials used, with a concise description and the critical and strategic raw materials each contains, their total weight, a breakdown by weight or percentage and the secondary resources used (paragraph 13(a) to (d)).
AR 2 refers to Annexes I and II of Regulation (EU) 2024/1252, and AR 1 asks for the technical or biological distinction where relevant. Secondary resources are reported by weight or percentage of total key materials.
The 2023 E5-4 (paragraphs 28 to 32) applied when inflows are material. Paragraph 31 asked, in tonnes or kilogrammes, for the total weight of products and technical and biological materials, the percentage of sustainably sourced biological materials with the certification scheme and the cascading principle, and the weight and percentage of secondary components and materials.
Products and Packaging: The First Half of E5-5
The 2026 E5-5 requires qualitative or quantitative information on the expected durability and the repairability of key products and the designed recyclability rate of key products and their packaging (paragraph 15(a) to (c)). AR 3 gives the equation for the rate.
The 2023 E5-5 paragraph 36 applied when outflows are material. It asked for expected durability against the industry average, a reparability rating using an established rating system where possible, and rates of recyclable content in products and packaging.
Waste: The Second Half of E5-5
The 2026 E5-5 asks for waste streams, total weight, the percentage diverted and the percentage directed to disposal, each split into hazardous and non-hazardous, and the percentage with an unknown final destination (paragraph 16(a) to (e)). Diverted waste splits into preparation for reuse, recycling and other recovery; disposal into incineration, landfill and other disposal.
Paragraph 17 covers radioactive waste by reference to Article 3(7) of Directive 2011/70/Euratom. AR 5 asks for weight in the original state, not dry weight. AR 6 counts incineration with energy recovery as other recovery only under point R1 of Annex II of Directive 2008/98/EC.
The 2023 E5-5 paragraphs 37 to 39 used tonnes or kilogrammes, the total and percentage of non-recycled waste, the composition of waste, and hazardous and radioactive waste, with no item for an unknown final destination.
Anticipated Financial Effects: E5-6 and Its Replacement
The 2026 version has no E5-6: anticipated financial effects are required through paragraph 27 of ESRS 2 and are not a separate E5 disclosure requirement. The 2023 E5-6 (paragraphs 41 to 43) asked for quantification before actions or qualitative information, the effects, impacts, dependencies and horizons, and the assumptions (paragraph 43(a) to (c)).
Under ESRS 1 Appendix C of the 2023 version, all undertakings may omit E5-6 for the first year and report qualitative information only for the first three years. Under Delegated Regulation (EU) 2025/1416, wave-one undertakings may omit E5-6 for the first three years. The phase-in provisions for anticipated financial effects cover both.
The 2026 phase-in for paragraph 27 of ESRS 2 reads: wave one before financial year 2028 and quantitative information before financial year 2030; for other undertakings the first two and the first four financial years (ESRS 1 paragraphs 125 to 127).
What the 2026 Version Changes
Delegated Regulation (EU) 2026/1563 keeps the three E5 sub-topics but deletes E5-6, drops the IRO-1 paragraph, hands policies, actions and targets to the general disclosure requirements and replaces the inflow, product and waste datapoints. The table lists each change with its version and provision.
| Change | 2023 version | 2026 version | Provision |
|---|---|---|---|
| Disclosure requirements | Six | Five | E5-1 to E5-6 against E5-1 to E5-5 |
| IRO-1 paragraph | Paragraph 11 | None | ESRS 1 paragraph 29; ESRS E5 |
| Policies, actions, targets | MDR-P, MDR-A, MDR-T | GDR-P, GDR-A, GDR-T, with paragraph 9 added | ESRS E5 paragraphs 8 to 11 |
| Inflows | Total weight of products and materials, biological share, secondary share | Key materials, critical and strategic raw materials, total weight, breakdown, secondary resources | 2023 paragraph 31; 2026 paragraph 13 |
| Products | Durability against industry average, reparability rating, recyclable content | Durability, repairability, designed recyclability rate | 2023 paragraph 36; 2026 paragraph 15 |
| Waste | Tonnes or kilogrammes, non-recycled share | Percentages of total waste, unknown final destination, R1 condition | 2023 paragraph 37; 2026 paragraph 16 and AR 6 |
| Anticipated financial effects | E5-6 | ESRS 2 paragraph 27 | 2023 paragraphs 41 to 43; phase-in provisions for anticipated financial effects |
| Datapoint totals across all standards (not E5 alone) | 783 | 292 | EFRAG draft list; 783 to 292 'shall' datapoints across all standards |
| FY 2026 version choice | One option | One option | Article 2 of 2026/1563; the choice between the versions under the revised (simplified) ESRS |
The changes apply to financial years beginning on or after 1 January 2027, and optionally to FY 2026 (Articles 2 and 3 of Delegated Regulation (EU) 2026/1563). EFRAG gives the technical advice that the Commission takes into account when it adopts the ESRS (Article 49(3b) of Directive 2013/34/EU).
Across all standards there are 783 'shall' datapoints in the 2023 set and 292 in the 2026 set (195 net of conditional datapoints), according to EFRAG's draft list of datapoints, which is non-authoritative and must not be used as a checklist.
The general disclosure requirements and paragraph 27 sit in ESRS 2 general disclosures in the 2026 version.
How to Prepare the ESRS E5 Disclosures
Prepare the E5 data in six steps, in this order, and keep the paragraph and the source record behind each figure for the assurance provider.
- Confirm the scope and the first financial year with the CSRD scope check.
- Choose the version for FY 2026 and state it in the statement (Article 2 of Delegated Regulation (EU) 2026/1563).
- List the key materials and their inflow weights, with the critical and strategic raw materials in the 2026 version, and record whether each figure is measured or estimated.
- Collect durability, repairability and designed recyclability data for key products and their packaging.
- Collect waste by stream and operation type, in original weight, with the share of unknown final destination.
- Place the figures in the sustainability statement, which is subject to limited assurance only (Article 34(1), second subparagraph, point (aa) of Directive 2013/34/EU as replaced by Article 2(12)(a) of Directive (EU) 2026/470).
For the steps across all standards, see our CSRD compliance plan.
How Resource Use Connects to the Other Topical Standards
ESRS E5 is the standard where the technical flows of materials and waste are reported, and the other topical standards cover the pollution, climate, water, biodiversity and people effects of those flows. Paragraph 7(a) to (f) of the 2026 E5 names six of them.
Paragraph 5 of the 2026 E5 lists the EU frameworks the standard takes into account, among them the Waste Framework Directive and the ecodesign rules for sustainable products.
- Paragraph 7(a) names ESRS E1 Climate change.
- Paragraph 7(b) names ESRS E2 Pollution.
- Paragraph 7(c) names ESRS E3 Water.
- Paragraph 7(d) names ESRS E4 Biodiversity and ecosystems.
- Paragraph 7(e) names ESRS S3 Affected communities.
- Paragraph 7(f) names ESRS S4 Consumers and end-users.
ESRS E5 Questions
Four questions recur about ESRS E5.
Is ESRS E5 mandatory?
Under the 2023 version one paragraph, paragraph 11, is reported in every case, and the rest applies if the topic is material (ESRS 1 paragraphs 29 and 30). Under the 2026 version E5 is reported if the topic relates to material impacts, risks and opportunities (ESRS E5 paragraph 2).
How many disclosures does E5 contain?
ESRS E5 has six disclosure requirements in the 2023 version and five in the 2026 version, where E5-6 is deleted.
What happened to E5-6?
The 2026 version deletes E5-6, and anticipated financial effects are required through paragraph 27 of ESRS 2. Phase-ins for the effects sit in paragraphs 125 to 127 of ESRS 1.
Is waste with an unknown final destination reported?